Typical Production cycle in Process Industry

...Previous

2.       Goods issue against the Process order using MIGO Transaction

Goods issue generally happens from store against the PO with the movement type 261

Once goods issue from the stores is over, the document number will be generated as below

Now go to process order and check the order status “GMPS” will appear, that means Goods Movement Posted

Now Production process was started and completed. We are going to give confirmation using CORK transaction

3.       Confirmation using CORK  Transaction

Once you enter, the yield quantity you have to confirm

Here in MM01, Quality Management views we have to activate the inspection lot origin “04” for inspection triggering while making Goods receipt using 101 transaction. The following procedure has to be adopted.

Select Inspection set up tab and activate  04 inspection type.

This activity has to be done at the time of creation of Master (MM01)

4.       Goods Receipt using MIGO with movement type 101

If you check this screen the outputs finished product 1 and co product 1 with the quantities viz., 50 and 60 will be there. We have activated QM view only for FG 1 and not for BP 1 material. So once GRN was made the material FG 1  will be automatically moved to Quality inspection and BP 1 will be moved to “unrestricted use”.

At the time of GRN we are creating the batch for FG 1 as “FG00000001”

For BP 1 we are creating Batch as “CO00000001”. The batch can be created at the time of creation of Process order also.

Here we are mentioning the storage location for the final products “0004”

Once GRN made the document number will be generated for Accounting updates

Click here to continue...

 Please send us your feedback/suggestions at webmaster@SAPFunctional.COM 

HomeContribute About Us Privacy Terms Of Use • Disclaimer • SafeCompanies: Advertise on SAPFunctional.COM | Post JobContact Us  

Graphic Design by Round the Bend Wizards

footer image footer image