Typical Production cycle in Process Industry

...Previous

Here we have to mention the Person responsible and standard value type “SAP1 – Normal Production”.

Here we are planning to give the controlling area and cost center. Finally save the data. The same procedure has to be repeated for CRC-002

3.       Create Recipe using resource and material in T-code C201

In the above screen we have to enter the material we want to produce “FG 1”, and give the plant code and profile “PI01” then enter.

In the recipe header we have to enter the status as “4” and Usage as “1”  , go for Operations screen

Here we have to call the resource and the description details, for example in reactor CRC-001, the operations like Heating and transfer process will be carried out the same has been explained in this description field. As per standard value key we have to give the duration for the operation time and labor time. Both will be taken for scheduling.

In the material tab, we have to enter the version for the BOM and usage details, after that we have to enter the list of raw materials required for making 50 kg of the FG 1 product. Here co-product is generating so we have to give the co-product “BP 1” 60 L as “Negative” producing after the process (NOT as INPUT) and activate as Co-Product by selecting the line item and press items tab and  select co-product tab.  

In the header level line item we have the base quantity i.e Finished goods quantity, give 50 and save

Now Recipe is ready.

4.       Create MIC using QS21 transaction

Click here to continue...

 Please send us your feedback/suggestions at webmaster@SAPFunctional.COM 

HomeContribute About Us Privacy Terms Of Use • Disclaimer • SafeCompanies: Advertise on SAPFunctional.COM | Post JobContact Us  

Graphic Design by Round the Bend Wizards

footer image footer image